Project Board meetings should be regular, scheduled and aligned as much as practical to the organisation’s financial reporting cycles, so that the project manager can give timely information on project progress and costs, and to escalate issues beyond their delegation. Most digital project boards meet on a monthly basis and at key decision points, but the frequency of meetings should be adapted to project pace and risk (11), with the possibility of a higher meeting frequency, for example, when the project is close to go-live or release.
The content of board meetings is often influenced by the project manager, supported by key topics in project reports. To keep the board focused on decision-making, reports should focus on exceptions to planned progress, changes to scope, risks and relationships (11). The agenda and supporting project reports will need to adapt to maintain a focus on the critical decisions needed to progress the project (23, 43).
Production of reports for the board divert resources from other project activities. The SRO needs to balance information requests from the board to the project team, with the effort needed to produce them. There is also a tension in the timeliness of information for project reporting. Where possible, board meetings should be scheduled to minimise the lag between report data and the meeting. The board should regularly reflect on whether all sections of project reports play a role in the decisions the board makes. Removing redundant sections of reports can make it easier to focus on key information and reduce a project reporting burden. Focus for reports should be on exceptions, earned value, and differences between planned and actual progress.
The board maintain responsibility for obtaining the information they need to govern project progress and may need to work with the project manager to ensure they obtain necessary information, moving past a passive information-consumption attitude. Technical jargon should be avoided in reporting in favour of language that allows the board to make trade-off judgements on the business logic and strategic alignment of the project. Board members may have to actively seek outside information if they are to be suitably informed, for example by attending regular project meetings (23, 43), engaging directly with users and operational mechanisms (e.g. walking the shop floor), or conducting informal discussions with stakeholders.
The following table lists some of the common documentation used to support project board formation and decision making. Governance tips from an SRO are also included later in this document.
| Artefacts | Core elements |
|---|---|
| Project Board Terms of Reference (ToR) | The ToR should clearly articulate the scope of the board's remit, authority of the board and its positioning with corporate governance forums and other project governance mechanisms. It should clearly define board roles, potentially including a RACI matrix (responsible, accountable, consulted, informed). The ToR needs to place strongly restrictive conditions on board members use of delegates or proxies. Escalation processes and criteria for exception reporting should be included. These should detail the specific delegated time, cost, quality, or scope change limits that the project manager is delegated to approve, and which must be escalated for board approval. |
| Business Case | It specifies why the project is required, its objectives, intended benefits, and solution strategy. It specifies the parameters within which the project operates (e.g. time, budget, scope), which provide the baseline against which project delivery performance can be measured. |
| Benefits Realisation Plan (BRP) | A BRP outlines how the benefits of an investment will be achieved and measured. Its purpose is to ensure an investment delivers its intended value. The BRP describes the context, structure, and approach to the realisation of planned benefits and is typically developed alongside the business case (at least to initial draft level) to ensure there is a clear plan for the realisation of benefits outlined in the business case. See the DTA's Benefits Management Policy and Toolkit for more information. |
| Benefits Map | A benefit map links the key project benefits and enabling changes on which benefits realisation depends to an organisation's strategic objectives. Benefit mapping and the resulting Benefits Map, is an iterative process which should be revisited multiple times during the investment. This will ensure that unintended consequences and disbenefits are accurately factored into the investment planning process and that the investment remains on track to realise intended benefits. See the DTA's Benefits Management Policy and Toolkit for more information. |
| Stakeholder Impact Assessment | A Stakeholder Impact Assessment identifies who is affected by the project and evaluates the nature of the impact. It assesses relative power of each stakeholder, their interests and readiness for change. The assessment can be utilised to inform engagement strategies and risk mitigation plans. |
| Project Board Papers | Project board papers are produced by the project manager, focusing on decision-making and exception reporting. They are designed to support decisions escalated to the board. They should make clear recommendations, clearly noting the action required (e.g. note or approval). They should be distributed to the board at least 3 days in advance [3 - DTA]. Standardising reporting across an agency is recommended to help board members can easily consume information [14, SRO]. |
| Assurance Plan | Agencies are required to plan for assurance by applying the Key Principles for Good Assurance and meeting minimum assurance requirements applicable to the tier of the investment. The Assurance Plan is agreed with the DTA and submitted to Cabinet for approval as part of the proposed investment. The Assurance Plan should be regularly reviewed by the board, at least as often as the relevant tier requires. This is key to ensuring the plan continues to be fit-for-purpose. See the Assurance Framework for Digital and ICT Investments for more information. |
Guidance for Senior Responsible Officials
Assurance Research Series 02
Project governance is "part art, part science", which can be facilitated by following principles to guide the design of digital project governance boards. This research has revealed and collated common challenges faced by digital project governance boards and some recommendations to resolve them. These are organised by the challenges in composing digital project boards (Table 7), and challenges with scope and performance (Table 8).
We group challenges by the three pillars of project board composition: Structure, People and Information flows. We close this section out addressing when a project's performance or feasibility is at risk.
| Challenge | Description | Recommendations to Resolve |
|---|---|---|
| Structural misalignment | Existing organisational structure does not align with the structure needed to support the digital project. For example, in digital health transformations it can be useful to get input from surgeons across health services, but there is not necessarily an organisational mechanism in place for that to happen. | Integrate informal mechanisms and proactive management by key individuals to enable practical governance (beyond the formal structures and meetings). |
| Cross-agency or complex stakeholder environment |
|
|
| Convoluted or rigid governance structures |
|
|
| Insufficient capacity | SRO or board members unable to devote sufficient time to role due to overcommitment. |
|
| Challenge | Description | Recommendations to Resolve |
|---|---|---|
| SRO experience | The SRO does not have the experience in digital projects to confidently guide the project. | |
| Board skills and capability | The collective capabilities and skills of the board do not align with the project's objectives and desired outcomes. |
|
| Agile Literacy Gap | Board members do not fully understand agile project methodologies and associated governance requirements. |
|
| Over-reliance on third parties |
|
|
| Commitment |
|
|
| Dominant or silent members |
| |
| Toxic behaviour |
|
| Challenge | Description | Recommendations to Resolve |
|---|---|---|
| Information supporting decision-making |
|
Areas to address:
|
| Challenge | Description | Recommendations to Resolve |
|---|---|---|
| Benefits definition and oversight | Project benefits are not adequately defined and/or regularly monitored. |
|
| Benefits difficult to attribute to the project in isolation | Project is either one of many initiatives to achieve a broader benefit, is the enabler for other projects to achieve direct benefits, and/or the majority of benefits will be realised well after (even decades after) the project has finished. |
|
| Optimism Bias | An overly optimistic view as to what can be realistically achieved with the scope of a project, groupthink, lack of curiosity. |
Continually question:
|
| The project is built on flawed foundations | Flawed foundations can include:
|
|
| Ineffective decision-making | Decision-making is:
|
|
| Informal decision-making |
|
|
Source: Assurance Research Series 02 | DTA | UQ
To successfully meet this criterion, you need to:
This self-assessment tool is designed to help you reflect on the effectiveness of your digital project governance board. You can complete it on your own, or use it as a group exercise with your board members – either as an open process or subject to confidentiality. It can be undertaken at any time—such as when establishing a new board, at regular intervals throughout the project lifecycle, or following significant changes to the project or board composition. Periodic use of this tool helps track progress, identify strengths and areas for improvement, and support a culture of continuous improvement in governance.